NUMBER 202 DATE: 05/19/00
CENTER ACTIVITIES
Sector Processing Center (SPC):
During March, EUM, JMA, CSU and AES processed more than 92% of A data into B1/B2 data.
Normal operations for March were reported by EUM, JMA, CSU and AES.
NOA processing of B2 data has resumed with data for October and November 99 being delivered this past month. Work has started on revised software to handle the NOAA-15 format change. CSU has processed and shipped the GOES-10 B2 through September 99.
CSU is still supplying the AC data for GOES-8 until AES revises their format. AES has reported completion of this revision, but the new format has not be confirmed by the SCC.
Satellite Calibration Center (SCC):
AC data were received for March 00 from NOAA-14 (AVHRR and HIRS), GOES-8, GOES-10, METEOSAT-5, METEOSAT-7 and GMS-5. BC data for January 99 for GOES-8, GOES-10, METEOSAT-5, METEOSAT-7 and GMS-5 were shipped to the GPC.
Currently, AC data for NOAA and GMS are the only ones received on media (Exabyte and CD-rom, respectively); all other AC data are received and the BC data are sent via Internet.
All BC reports now include normalization for the visible, standard infrared and "split-window" infrared channels (except METEOSAT which does not have a split-window channel), and the "water vapor" channels.
Global Processing Center (GPC):
The GPC continued to receive B2 data, BC data and correlative data in a routine manner; all of these data, except for the BC data and one B2 dataset, are currently received on media.
The GISS LAN has now been re-configured to a more stable and predictable form. In-house software to write all ISCCP datasets on the tape silo from workstations is completed, except for some error checking diagnostics. Now the tape cataloging system must be moved to workstation with a new software system.
Production of NOAA-14 (preliminary) B3 data is current as of April 98; B2 data have been received through November 99. Final B3 data have been produced through April 98. The polar orbiter processing code has been ported to workstation.
Production of NOAA-12 (preliminary) B3 data is current as of April 98; B2 data have been received through December 98 (the last). Final B3 data have been produced through April 98. The polar orbiter processing code has been ported to workstation.
No NOAA-15 B2 data have been received as yet.
Production of GOES-8 (preliminary) B3 data is complete for January 96 through December 97. The AES-format-version of the GOES-8 B3 processing software has been ported to workstation.
All (January 96 through July 98) GOES-9 B2 data has been received from CSU. The formatting software is in final testing on workstation.
The GOES-10 B2 data for July 98 through September 99 have been received. The formatting software is in final testing on workstation.
Deliveries of B2 data from METEOSAT-5 (at 63E) are current, but processing has not resumed.
Production of METEOSAT-6 (preliminary) B3 data is complete through June 98. Final B3 data have been produced through April 98.
Production of METEOSAT-7 (preliminary) B3 data has not commenced; however, the formatting software has been completed (it still needs to be ported to workstation, however). The documented spectral response functions for METEOSAT-7, published in the latest B3 documentation and posted on the ISCCP Web page, are incorrect. The correct spectral response functions will be posted to the Web page as soon as processing resumes.
Production of GMS-5 (preliminary) B3 data is complete through April 98; final B3 data have been produced through April 98.
All B3 processing software and the B3 data formats have been revised to include, as of January 96, the normalization coefficients for all the additional spectral channels. The re-calibration software has now been ported to workstations and is undergoing final testing.
TOVS correlative data processing is complete through April 98.
Production of the ice/snow correlative dataset on workstation is complete through September 99. The data for 98 will be delivered to the archives once the tape-writing procedures are finished.
The VIS calibration for NOAA-11 has been changed for the period January through September 94 to eliminate a spurious darkening trend, detected in the cloud product results and confirmed by comparison with NOAA-12. The D-data for January - December 94 have now all been re-processed and the spurious trend has been eliminated. The "calibration gap problem" from September 94 to February 95 has also been resolved. D-data for January - August 95 (without GOES-8) have been processed. All data products are currently delivered on media.
Two CDs of D2 data are now available from NASA Langley, covering 83-88 and 89-93.
Data now available on the Web site are monthly mean data for July 83 through December 93 and climatology results based on the period July 83 through June 94. The ISCCP World Wide Web Home Page can be accessed at URL
http://isccp.giss.nasa.gov
ISCCP Central Archive (ICA):
The ICA continued to receive B1 data from NOA, AES, EUM, CSU and JMA and B3 and D data from the GPC in a routine manner.
SATELLITE HEALTH
The health of GOES-8, GOES-10, GMS-5, METEOSAT-5, METEOSAT-7, NOAA-14 and NOAA-15 remained good. GOES-11 was successfully launched on 2 May 00 and will serve as backup to GOES-8 and GOES-10. Launch of NOAA-L is set for August 00. EUMETSAT has announced plans to continue operations of METEOSAT-5 at 63E (Asian sector) through 01, one year longer than originally planned for INDOEX. Moreover, if the launch of METEOSAT Second Generation (MSG), scheduled for late 00, is successful and both METEOSAT-6 and METEOSAT-7 are still healthy, one of these latter satellites will be moved to continue coverage of the Asian sector beyond 01.
DATA DELIVERED
Stage B3: July 83 - April 95 (11.8 years)
Stage CD: July 83 - December 97 (14.5 years)
Stage D1: July 83 - August 94 (11.2 years)
Stage D2: July 83 - August 94 (11.2 years)
Satellite and Data Delivery Charts
| Satellite Network 7/83-12/94 | Satellite Network 1/95-12/05 |
| B Level Data Products 7/83-12/94 | B Level Data Products 1/95-12/05 |
OPEN ITEMS
* Delivery backlogs for B2 data (NOAA-14 = 4 months, NOAA-15 = 15 months, CSU = 6 months).
* Delivery backlog for B3 data = 53 months (with respect to planned schedule). B3 data for 142 months have been archived.
* Delivery backlog for new DX/D1/D2 data = 61 months (with respect to planned schedule). D1/D2 data for 134 months have been archived.