ISCCP PROJECT STATUS REPORT

NUMBER 224 DATE: 03/13/02

CENTER ACTIVITIES

Sector Processing Center (SPC):

During January, EUM, JMA, CSU and MSC processed more than 98% of A data into B1/B2 data.

Normal operations for January were reported by EUM, JMA, CSU and MSC. No report was received from NOA.

CSU is still supplying the AC data for GOES-8 because the SCC has not accepted the revised format from MSC.

Satellite Calibration Center (SCC):

AC data were received for January 02 from NOAA-16 (AVHRR and HIRS), METEOSAT-5, METEOSAT-7, GMS-5, GOES-8 and GOES-10. BC data for November 01 for METEOSAT-5, METEOSAT-7, GMS-5, GOES-8 and GOES-10 were shipped to the GPC; these are the first results based on NOAA-16. Processing of the normalization for the "water vapor" channels is delayed to accommodate changes between NOAA-14 and NOAA-16 HIRS data.

AC data for GMS are received on CD-rom; all other AC data are received and the BC data are sent via Internet.

All BC reports now include normalization for the visible, standard infrared and "split-window" infrared channels (except METEOSAT which does not have a split-window channel), and the "water vapor" channels.

Global Processing Center (GPC):

The GPC continued to receive B2 data, BC data and correlative data in a routine manner. All of these data are now received by Internet, except for the B2 data from NOA. All data (except DX) from the GPC are delivered by ftp to NOAA/NCDC and to NASA Langley.

All NOAA-15 B3 data have been delivered.

Deliveries of B2 data from NOAA-16 are current. Processing will require more extensive software changes than for NOAA-15 because of the six channels available.. Also, the cloud detection algorithm and the DX-format will have to be revised before these data can be used.

Deliveries of B2 data from GOES-8 are current. Production of GOES-8 (preliminary) B3 data is complete through September 01. Final B3 data have been produced through December 99.

Deliveries of B2 data from GOES-10 are current. Production of GOES-10 (preliminary) B3 data is complete through September 01. Final B3 data have been produced through December 99.

Deliveries of B2 data from METEOSAT-5 (at 63E) are current. Production of METEOSAT-5 (preliminary) B3 data is complete through September 01, except for April 01 which is missing. Final B3 data have been produced through December 99.

Deliveries of B2 data from METEOSAT-7 are current. Production of METEOSAT-7 (preliminary) B3 data is compete through September 01. Final B3 data have been produced through December 99.

Deliveries of B2 data from GMS-5 are current. Production of GMS-5 (preliminary) B3 data is complete through September 01, except for February 00 and 01, which have problems. Final B3 data have been produced through December 99.

TOVS correlative data processing is complete through June 00.

Production of the ice/snow correlative dataset is complete through September 01.

DX/D1/D2 data processing is complete through December 99. A complete investigation is underway to identify and fix (if possible) all small processing errors to improve the homogeneity of the whole D dataset for monitoring of climate variations. All data products are currently delivered by ftp to the ICA and NASA Langley (except for DX data).

Two CDs of D2 data are now available from NASA Langley, covering 83-88 and 89-93. A new CD covering 94-98 will be released within the next month or two.

The survey of midlatitude cyclones that merges re-analysis and ISCCP cloud data has been completed covering the period from 1983 through 1998. A survey of deep convection, including statistics of cloud properties and their evolution over system lifetimes has begun. These data will be merged with TRMM precipitation observations.

Data now available on the Web site are monthly mean data for July 83 through December 99 and climatology results based on the period July 83 through December 99. The radiance calibration tables have been updated through September 01. The ISCCP World Wide Web Home Page can be accessed at URL

http://isccp.giss.nasa.gov

ISCCP Central Archive (ICA):

The ICA continued to receive B1 data from NOA, MSC, EUM, CSU and JMA and B3 and D data from the GPC in a routine manner.

SATELLITE HEALTH

The health of GOES-8, GOES-10, GMS-5, METEOSAT-5, METEOSAT-7 and NOAA-16 remained good. METEOSAT-6, GOES-11 and GOES-12 are in stand-by mode. Envisat was successfully launched on 28 February 02, Aqua is scheduled for launch in April 02 and ADEOS-II is scheduled for launch in November 02.

DATA DELIVERED

Stage B3: July 83 - December 99 (16.5 years)

Stage TV: July 83 - December 99 (16.5 years)

Stage SI: July 83 - December 99 (16.5 years)

Stage D: July 83 - December 99 (16.5 years)


Satellite and Data Delivery Charts

Satellite Network
B Level Data Products


OPEN ITEMS

* Delivery backlogs for B2 data (none).

* Delivery backlog for B3 data = 19 months (with respect to planned schedule). B3 data for 198 months have been archived.

* Delivery backlog for DX/D1/D2 data = 19 months (with respect to planned schedule). D1/D2 data for 198 months have been archived.